Construction Timeline

Upcoming Construction Milestones! 
These dates are all subject to change

Phase 2: The New Addition
Expected Completion Date:  October 12th, 2011

April 5th, 2011-  Structural Steel is delivered and installation of it begins
April 15th, 2011-  Pouring the concrete slab/ foundation
May 27th, 2011-  Installation of Roof
July 13th, 2011- Drywall
July 27th, 2011- Prime and Paint
August 3rd, 2011-  Millwork Install
August 29th, 2011-  Flooring Install
   
Phase 3: Renovation of old Building
Expected Completion Date:  January 18th, 2012

September 30th, 2011- Start Phase 3
October 14th, 2011- Selective Demolition
November 2nd, 2011- Drywall
November 14th, 2011- Prime and Paint
November 21st, 2011- Millwork installation
December 13th, 2011- Flooring Install